Description:

Change control is defined as identifying, documenting, approving or rejecting, and controlling changes to the project baselines. [PMBOK]

Performing integrated change control is the process of reviewing all change requests, approving changes, and managing changes to the deliverables, organizational process assets, project documents and project management plan. [PMBOK]

Please note that information classified as Protected (per the Data and Information Security Classification standard) is only accessible to Government of Alberta Employees. External users are therefore not able to download this document. To request access, please contact us: imt.policy@gov.ab.ca.